Brownfield Projects Engineering
Brownfield engineering relates to engineering activities (e.g. design, commissioning) that interface to, upgrade or modify an existing operation or plant. Performing a brownfield engineering project requires an approach that is different to greenfield projects. In greenfield projects, where work is being completed on a new site, the plant is not currently operating and for the most part provides a blank canvas to work within. In contrast to this, projects undertaken on a brownfield site need to work within existing plants and their production and shutdown requirements, at all times targeting to minimise disruption to the operation.
Some of the many challenges faced in brownfield engineering projects include assessing existing electrical, structural and mechanical capacities for expansion, gaining access for construction and cranage within an operating site, and the inherent safety implications this may present, whilst working to minimise any required shutdown periods.
When Orana Engineering carries out brownfield engineering projects, wherever possible any new plant or equipment is in line with current site standards to ensure that onsite operators and maintainers remain familiar with their systems and that the availability of site spares is not compromised. If this is not possible we place a strong focus on ensuring operators and maintainers are familiar with new technology being installed and identifying any new critical spares needing to be carried by site to minimise plant outages in the event of breakdown.
We have carried out multi-discipline brownfield engineering projects for coal, metalliferous, oil and gas clients as well as industrial and commercial clients. Explore the case studies below for more information on brownfield engineering services by Orana Engineering.
Orana Engineering Brownfield Project Engineering
UG Conveyor Installations - MG Mechanical Installation
Detailing the installation of mechanical equipment and conveyor structures is one of the final steps for completing a maingate drive-head design. Installations designed by Orana Engineering for Glencore’s Oaky No.1 underground coal mine included detailing drive arrangements, transfer stations, take-up units, maintenance equipment and the overhead structures supporting the carry belt.
Mechanical design must consider a number of factors, including meeting the required operating capabilities, allowing for unimpeded access along travel roads and maintaining minimum belt curves. Often equipment is relocated from previous installations with minor modifications in transfer angle and number of drives. Orana Engineering has developed unique methods for completing this type of design, enabling us to keep total costs down for our clients.
Crib Hut Wind Load Review
Orana Engineering was contacted by Glencore for assistance in determining ground anchoring of three mobile crib huts at its Rolleston Coal Mine. The objective of Orana Engineering’s investigation was confirmation of applicable regional wind loads on each structure and requirements for external hold-downs with respect to sliding and overturning forces.
To assess anchoring options, calculation and analysis of wind forces on the mobile crib huts was performed using AS/NZS1170.2 for loading with various earth anchor types evaluated while also taking into consideration soil properties and ground compaction.
Based on structural engineering principles and calculations, and in consideration of Australian Standards and industry best practice, it was determined that all the mobile crib hut structures required anchoring to prevent sliding or overturning. Recommendations for the most appropriate type of ground anchor, along with general stipulations for application and installation of the these, was documented and presented to the client upon conclusion of Orana Engineering’s evaluation.
Village Kitchen Upgrade
The Village Kitchen at Glencore’s Hail Creek Mine camp was scheduled for upgrade with Orana Engineering engaged to provide engineering support for electrical, civil and building works, including a new shed. A site visit was conducted to determine the scope of the upgrade and to collect site information comprising photos, drawings, measurements and location of water and gas services.
From the information gathered, Orana Engineering provided engineering design and project management of the Village Kitchen upgrade including a new shed distribution board, concrete slab, layout and connection of services to the new shed and prepared a detailed scope of work document for tendering purposes.
Orana Engineering design drafters produced RPEQ certified GA and concrete drawings showing details of services to be relocated, a slab and loading dock drawing, a new single line diagram for the distribution board, and revisions to existing distribution board drawings.
Rajant Network
Glencore planned to install the CAT MineStar Terrain Office system at its Oaky Creek Coal Mine to support GPS positioning and live maps in CHPP stockpile dozers. As part of the upgrade, mine infrastructure and dozers required hardware installation to connect the dozers to the site network and enable communication with MineStar servers. In line with other Glencore sites, it was chosen to implement a Rajant wireless network to cover stockpiles and provide connectivity between dozers and the network.
Orana Engineering was engaged to provide electrical and Operational Technology (OT) engineering design, configuration and drafting support for the CAT MineStar GPS implementation including preparation of three new virtual servers for various applications. Orana Engineering electrical engineers developed a scope of work which provided an overview of the onsite electrical installation works required to be carried out by others with supply, installation, testing and commissioning project managed by an Orana Engineering electrical and control systems engineer.
Ash Water Return Pipeline Replacement
Ash slurry at CS Energy’s Kogan Creek Power Station is pumped to various locations around site via a pipeline originally installed for delivery of service water from the power station to the crusher area. With proposed pumping equipment capable of higher pressure output, a project was set up to review the engineering calculations and potential risks.
Orana Engineering was engaged to conduct concept design investigations considering options for repair or replacement of the pipeline. Outcomes from the review were provided to CS Energy summarising options considered and proposing the use of carbon steel (potentially lined for corrosion resistance) as the optimal replacement for fibreglass piping. Advantages and disadvantages of carbon steel were also presented such that the client was fully apprised of its properties.
As only limited drawings of the existing pipeline were available, Orana Engineering design drafters produced pipeline general arrangements for information.
TLO Bin Support Repairs
Orana Engineering assisted Glencore's Clermont Coal with an engineering review of the structural integrity of head end support stools connected to its train load-out (TLO) bin ring beam as material build-up at the top of the bin cone had resulted in corrosion of several lower stools connected to the ring beam. Orana Engineering presented recommendations for temporary stiffening solutions and a repair methodology to restore conveyor supports to original design capacity.
Following the initial review, Clermont Coal requested that Orana Engineering undertake a further structural review of the TLO bin to analyse the effect of scaffold arrangements to be constructed on the bin and to confirm overall structural integrity with the additional applied loads.
Orana Engineering design drafters developed a concept design 3D model of proposed bracing including finite element analysis (FEA), and RPEQ certified detailed drawings for TLO column repairs were also delivered to the client.
IBC Stand for Pump Suction Height
Glencore’s Hail Creek Coal Mine engaged Orana Engineering to develop the engineering design for a stand to elevate a 1,000 litre IBC from ground level, enabling the content to gravity feed to the pump suction during a major upgrade project.
Design considerations by Orana Engineering included the process and materials relevant to the IBC location, raw material requirements and painting specifications based on site standards, positioning and fit of the IBC with existing equipment and infrastructure once elevated on the stand. Height requirements for gravity feed to pump suction connection and allowance for differential grouting of feet to account for concrete falls were also taken into account.
Orana Engineering design drafters generated a 3D model of the proposed design using AutoCAD Advance Steel for client review before developing a Navisworks Model of the IBC stand and completing engineering checks for load.
Final deliverables to the client included arrangement and fabrication detail drawings of the stand with RPEQ supervision.
Filter Press Installation
A filter press initially planned for Glencore’s Clermont Coal Mine was relocated for installation at Collinsville Coal Mine in a trial capacity to assist in reducing the amount of tailings produced from the wash plant.
Orana Engineering was engaged to provide engineering and drafting support for the filter press installation scope of work, to assess suitability of the Clermont detailed design for construction at Collinsville and to plan and implement arrangements for the installation.
Considerations to ensure a smooth installation at Collinsville included concrete design and a structural analysis. Calculations were also undertaken to determine design wind and earthquake loads for the site to Australian Standards AS/NZS1170.2 and AS1170.4.
Orana Engineering design drafters produced a new site plan showing set-out of the filter press slab with new and existing underground services detail incorporated, with RPEQ Supervision.
Fire Hydrant Extension
Personnel at Origin Energy’s Darling Downs Power Station contacted Orana Engineering seeking assistance in reviewing regulatory requirements of fire protection systems (detection, alarms, hydrants, emergency exits) relevant to areas of the site not fully protected by existing systems due to distance or obstruction.
Orana Engineering’s design was required to tie into the existing potable water fire line to supply a new fire hydrant / hose reel, while meeting operational fire-fighting requirements compliant with Australian Standards
Orana Engineering completed mechanical engineering, calculations and hydraulic modelling for review by a third party Fire Systems Designer and verification by an RPEQ Fire Engineer. Orana Engineering also undertook pipework design and drafting with RPEQ sign-off.
Deliverables to the client comprised a scope of work document, a testing / commissioning plan, budget estimate cost proposal for installation and building certification, and provision of a drawing set for the fire water extension.
Clarified Water Upgrade
Orana Engineering was consulted by Glencore’s Collinsville mine to assist with an upgrade of its CHPP washdown water distribution system. The CHPP clarified / raw water is supplied from either an anti-pollution pond or the raw water Sunwater pipeline, with the wash water distribution network delivering water to the yard area, CHPP washdown sprays, lime / flocculant dosing or conveyors for spray bars and washdown.
Following hydraulic modelling, Orana Engineering’s mechanical engineers delivered a design with improved flow and pressure, (increasing capacity from 375 to 700 cubic meters per hour) while structural engineers produced SpaceGASS modelling of pipe supports and 3D modelling of the discharge structural steel pipe rack. Additionally, a Functional Specification or Function Description was produced for integration of the design into the plant's control system.
Project deliverables included an Equipment Register, Scope of Supply, detailed Construction and Installation Scope of Work for Tender, Functional Description and detailed design drawings.
C22147 Water Destruction
Glencore’s Collinsville Open Cut mine utilises sprinklers to partially destroy Acid Mine Drainage (AMD) water generated. Existing sprinklers were effectively moving the AMD water, but at a slow rate. Orana Engineering was contacted for assistance in designing a system to increase the existing sprinkler arrangement from 67 to 200 units, capable of dewatering up to 9.45ML per day, while utilising a minimum of pumps and nozzles.
Orana Engineering mechanical and electrical engineers gathered data and undertook hydraulic modelling in developing a sprinkler design to increase water surface area while decreasing maintenance and failure rates of existing nozzles.
3D modelling of the design was presented to the client along with RPEQ supevised detail design drawings.
Anti-Pollution Pond Access
At the request of Glencore’s Collinsville Open Cut Mine, Orana Engineering provided a concept design for upgrade of aging infrastructure associated with the sites anti-pollution pond.
Orana Engineering provided a detailed design for installation of permanent handrail and barrier systems along the access pathway to mitigate hazards. The walkway bridge was identified as having inadequate support structure and was included in the proposed design, along with relocation of the existing pump pontoon and level sensors.
Orana Engineering design drafters produced 3D modelling for the installation which was provided to the client along with a general arrangement drawing of the new pontoon access, a fabrication detail drawing of the steelwork support and a civil and access ramp detail drawing, with RPEQ supervision.
Chain Feeder Modifications
The CPP chain feeder at Glencore’s Clermont Coal Mine required repair and the assistance of Orana Engineering was sought with development of an appropriate methodology and associated detailed design drawings.
Steel plates had been installed to cover the chain feeding system, which over time had been degraded by the dozer feeding the system chipping away at concrete footings. This caused exposure of the steel plate edge which subsequently caught on the dozer bucket. The result was a build-up of material around the chain, causing downtime to reinstate plates and clean up material.
Orana Engineering’s basis of design was for repair of the existing reclaim feeder concrete and development of suitable protection to reduce future wear damage and deterioration from dozer contact. Existing concrete footing drawings were revised to reference new concrete and steel detail and then issued for client review prior to finalising, with RPEQ supervision.
Sewage Treatment Plant Concrete Slab
CS Energy engaged Orana Engineering to provide engineering and drafting support in documenting the scope for onsite civil, electrical (earthing) and mechanical (shade sail and drain piping) supply and installation at its Kogan Creek Power Stations Sewage Treatment Plant.
The basis of design was provision of detailed design engineering of a bunded concrete slab to house two 22kL aerated tanks and a 20 foot container. The slab design was to include an effluent drainage system with a new discharge pipe to be connected to the existing underground wastewater drainage network. It was planned to remove existing tanks and pumps and the design scope prepared by Orana Engineering was to include details for filling and capping the residual drainage pipes and holes.
Design drawings generated by Orana Engineering personnel to support the scope of work included a general arrangement, a detailed drawing and a revised layout drawing.
Oily Water Pond
Origin Energy’s Talinga Gas Plant oily water system treats water created during the gas compression process. Effluent from the system is pumped into the water-gathering network, delivering water to the main water treatment plant.
Orana Engineering was engaged by Origin Energy to evaluate the oily water system and conducted a high level assessment of options to reduce the risk of uncontrolled release of contaminated water from the wetlands system that was controlled by interim means.
Outcomes were presented to the client summarising options to reduce or eliminate identified risks. Orana Engineering subsequently provided detailed mechanical and electrical design and drafting for the approved option.
Deliverables for the project included a basis of design document, detailed design and a revison of the Wetland Operations & Maintenance Manual.
Warehouse Delivery Area
Glencore’s Collinsville Open Cut Mine engaged Orana Engineering for assistance with engineering design of a new concrete slab to allow for driving, loading / unloading of forklifts and delivery trucks at its warehouse building. The design accounted for tie-ins to existing slabs and a surrounding security fence with cantilevered sliding gates on western and eastern sides of the area.
Orana Engineering’s involvement comprised gathering of additional site data and drawings on existing slabs, reviewing geotechnical and ground survey data for conditions in the area, liaison with the client and plumbers etc to confirm area runoff and underground services, as well as engaging vendors of precast concrete barriers, sliding gates and mesh fencing.
Preliminary sketches for client review and discussion were produced by Orana Engineering’s design drafting personnel, followed by concrete general arrangement and detail drawings and a structural detail drawing ‘issued for construction’ with RPEQ Supervision.
HV Tripping Supplies
Incitec Pivot’s Phosphate Hill site required replacement of tripping supplies for HV switchboards within its Ammonia Plant, Central Services, Phosphoric Acid Plant, Granulation Plant and Beneficiation Plant.
The switchboards had a dedicated 110VDC tripping supply with battery backup to power the HV protection relays and provide tripping supply power to HV circuit breakers. Without this back-up supply, circuit breakers would not open in the event of an electrical fault which could result in a catastrophic switchroom fire.
Existing tripping supplies were approaching end of life and with component failure likely to increase it was proposed to replace the tripping supplies during suitable shutdowns.
Orana Engineering was engaged to complete engineering design and to provide design drawings ‘issued for construction’. The Orana Engineering-assigned project manager had responsibility for vendor engagement, liaison with site planning and procurement personnel and site attendance during installation, commissioning and construction stages.
Gas Turbine No.1 Protection Relay Upgrade
Incitec Pivot was looking to replace an existing turbine generator pole slip relay unit at its Phosphate Hill Power Station. Existing pole slip relays had become obsolete and were at the end of their expected life. Pole slip relays perform a critical protection function for turbine generators and operation of a generator without its pole slip relay would pose an unacceptable risk. Consequences of relay failure on turbine generators would be multiple gas turbines being unserviceable and resulting in power shortages across the site.
The project scope involved replacement of Multilin 489 protection relay with new Multilin 889 for a 4.5MW gas turbine generator as well as integration of pole slip protection and a synchronisation check facility into the Multilin 889.
Orana Engineering’s input for the project included electrical engineering design, protection configuration, on site project management and commissioning.
Acid Unloading Leak Detection & CCTV Upgrade
To reduce the likelihood of potential spills in the sulphuric acid unloading area at its Phosphate Hill site, and to prevent consequential environmental and health and safety impacts, Incitec Pivot sought assistance from Orana Engineering with an upgrade of existing acid unloading leak detection and CCTV systems.
In consultation with Phosphate Hill site stakeholder personnel, Orana Engineering conducted an evaluation of available mitigation scenarios before recommending electrical and control methods which were considered to be the most cost effective resolution. Orana Engineering drafting personnel also produced detailed design drawings for the acid unloading leak detection and CCTV upgrade works.
HA Reclassification
Origin Energy’s Mount Stuart Power Station operated three power turbines driven by aviation kerosene and consideration was being given to converting these to operate on an alternative fuel source. Orana Engineering was engaged to conduct a hazardous area classification assessment covering re-classification of site areas relevant to the fuel conversion and to address handling of flammable gases produced as part of normal plant operation.
The objective was to establish whether an explosive atmosphere would exist around equipment following the proposed fuel conversion and to verify the classification and extent of hazardous areas in line with regulatory guidelines and standards AS 60079 Series and IE Model Code of Safe Practice, Part 15.
Upon conclusion of Orana Engineering’s assessment, the client was provided with a comprehensive Hazardous Area (HA) Classification Report confirming that ventilation at the plant was deemed adequate due to the outdoor location of most equipment and artificial ventilation within turbine and pump enclosures. Revised HA area classification drawings were also provided by Orana Engineering drafting personnel.
Brine Concentrator Drain Pump System
Orana Engineering was invited by MFE to provide an estimate for subcontract works for the Veolia Water brine concentrator drain pump system at Kenya Water Treatment Plant.
Brine concentrators at the plant periodically release high temperature and corrosive wastewater to floor sumps to control or monitor processes. The PVC pipework from floor sumps had become unserviceable due to the pipeline material not being rated for high temperatures. The existing drainage pipeline needed to be replaced with a durable system capable of withstanding high temperature corrosive wastewater.
Orana Engineering’s involvement in the project encompassed provision of engineering support (hydraulic, mechanical, civil and electrical design) and drafting support including revision of existing drawings and generation of new hydraulic, mechanical, civil and structural drawings with RPEQ supervision.
Brine Concentrator Engine Bay Crane
Veolia’s Kenya Water Treatment Plant contacted Orana Engineering for assistance with engineering design and drafting of a manual pull-along crane utilising existing support beams and able to travel in both long and cross travel directions. It was proposed for the fabricated cranes to be installed in each of the treatment plant’s three brine concentrator engine bays.
A member of Orana Engineering’s mechanical engineering team attended site to inspect existing infrastructure, take measurements and gather information. Upon return to Orana Engineering’s Chinchilla office the site data was reviewed, structural engineering calculations performed and information provided to the drafting office for translation to general arrangement and detailed design drawings suitable for fabrication purposes.
Orana 4 Pump Station
Veolia Water engaged Orana Engineering to look into options for a replacement pump station at its QGC Kenya Central Water Treatment Facility.
High level concept design investigations were initiated for options to replace the existing diesel driven manually controlled pump system for transferring brine from the site's Orana 4 Pond to the plant for treatment. Both a land based primed pump station and a water based floating pump station were given high level consideration. A detailed concept options report was developed for review and consideration by site stakeholders.
GCB Enclosure
Origin Energy sought assistance from Orana Engineering in providing a concept design for shade shelters to be retro-fitted to existing GCB enclosures at its Uranquinty Power Station in southern New South Wales. The objective of the shelters was to reduce rainwater contact with GCBs and the design to be such that shelters could be lifted off for periodic maintenance of GCBs.
A third party undertook 3D scanning of the existing cover structures and provided resultant scan data for 3D modelling by our design team. SpaceGASS modelling of the structures and analysis of compliance to Australian Standards was also conducted prior to provision of the new enclosure concept to Origin Energy for review. Upon receipt of design approval, Orana Engineering developed and issued a scope of work for supply and installation of the GCB enclosure shelters.
Secondary Spirals Monorail Design
At the request of Glencore Collinsville Coal Mine, Orana Engineering performed engineering design and drafting for a new monorail to be installed within the CHPP secondary spirals area. Orana Engineering’s assistance with the project included SpaceGASS modelling of the area and completing initial engineering and analysis for the proposed monorail while considering any effects on the existing structure and performing calculations and structural design checks to Australian Standards AS4100, AS1170 and AS1418.18.
Lifting vendors were consulted for monorail trolley and chain block options which ensured the most appropriate selections for the Collinsville application.
The designers at Orana Engineering produced a 3D model which was issued to the client for review and feedback. The monorail was fabricated and installed by others to Orana Engineering detailed design drawings and then load tested with subsequent deflection results meeting the requirements of Australian Standards.
Filter Line Upgrade
Process Engineering personnel at Glencore’s Collinsville Coal mine contacted Orana Engineering for engineering support on various projects associated with an upgrade of the piping in its ultrafine circuit. These included incorporation of tee-offs to in situ lines, and additional pipe runs.
Orana Engineering utilised existing 3D scan data to model a new pipe route and to provide concept general arrangement drawings to the client. With this information site personnel had sufficient data to liaise with vendors regarding new equipment selection.
Orana Engineering’s estimate also allowed for detailed design of RPEQ supervised drawings to allow the piping to be fabricated and installed.
Additionally, Orana Engineering conducted a structural assessment of the horizonal belt filter (HBF) to support a proposed viper roller unit.
Ash Water Treatment Plant
CSE Energy’s Kogan Creek Power Station identified that due to higher than normal rainfall its decant pond had neared capacity and was unlikely to evaporate in an acceptable timeframe by either natural means or with the assistance of fans. It was proposed to reuse the water on site, however due to a concentration of suspended silt the decant water required treatment before being returned to the plant. The solution was sourcing and installation of a containerised water clarification plant.
Orana Engineering was contacted for provision of electrical engineering design and support for power and control of the proposed ash water treatment facility as well as mechanical engineering input with pumping, piping and tank design for water supply and tie-in to existing infrastructure.
CHPP Projects - Water Balance
Orana Engineering was requested by the CHPP Manager Capital Projects at Glencore’s Collinsville coal mine to provide engineering and scoping assistance with respect to the mine’s underground water service repair and upgrade scope of work.
A member of the Orana Engineering mechanical engineering team attended site to liaise with onsite stakeholders, operators, plumbers and surveyors and to gather information on raw water and potable / fire water supply issues being experienced.
Upon return from site, a high-level engineering review was conducted along with detailing of raw water and potable / fire water scopes. Basic hydraulic modelling was also carried out to identify pressure spike issues and water hammer. Following review completion, the client was provided with a basis of design and a summary of Orana Engineering’s findings and recommendations.
CHPP Structural Repairs - CBN302
Glencore's Collinsville Coal Mine engaged Orana Engineering to develop a deconstruction safe work methodology for demolition and deconstruction of the CBN302 reject bin, along with appropriate risk assessment documentation based on the deconstruction methodology.
Key considerations were ensuring that the bin and structure supporting the conveyor head end were maintained in a safe and stable condition during deconstruction and that the risks of stored energy in the curved bin shell plates was managed through the steel thermal cutting process (avoiding steel plate spring-back hazards).
Orana Engineering’s basis of design determined the necessary steps to safely remove the redundant CBN302 reject bin.
Detailed design and engineering provided by Orana Engineering included 3D modelling of the reject bin and structural steelwork to assist in preparing the methodology images.
CHPP Structural Repairs - Clevis Plates
The CHPP Structural Supervisor at Glencore’s Collinsville Coal Mine requested the services of Orana Engineering in completion of a structural review and provision of a replacement methodology for the CCV101 Trestle Clevis Plates.
Orana Engineering’s consultation included a structural review of documents and existing drawings, identification of load-bearing elements and weak points, analysis of existing design and indication of necessary modifications. Additionally, the review included development of a strengthening plan and methodology utilising temporary bracing and support systems to lift the structure for trestle clevis plate replacement and avoid working under suspended loads using props.
Outcomes from the project included a letter of recommendation with instructions for the trestle clevis plates replacement works, including notes and methodology, mark-ups of site photos and drawings to illustrate the proposed replacement methodology.
CHPP Monorail Assessment
Glencore Coal Collinsville sought assistance from Orana Engineering in assessing multiple monorail designs within the CHPP area. The design review was to determine compliance with Australian Standards, including analysis of the structural capacity of each monorail, taking details from design drawings, 3D scans of the plant and physical measurements.
Fifteen monorails in total were assessed via visual and non-invasive means to determine their general state. Photos were cross-referenced with 3D scan data of the plant and existing structural drawings, with a structural assessment completed on all monorails to AS1418.18 using SpaceGASS and spreadsheet calculations.
Deliverables to the client upon conclusion of the study included a summary of design review results and recommendations for remedial action. Results from the assessment allowed updated certified as-built drawings of each monorail to be produced.
Compressed Air Upgrade
Anglo American’s Moranbah North CHPP operations personnel contacted Orana Engineering to investigate problems with low compressed air pressures and air flow rates. There were additional concerns regarding compressor reliability associated with the operation of equipment, valves, tooling, maintenance and instrumentation.
Orana Engineering conducted an onsite investigation which included preparing as-built drawings of the high-level compressed air distribution network within the CHPP. A review of historic transmitter data for the system was also carried out to identify issues and bottlenecks. System performance was also reviewed against site-checked pressures and engineering flow rate and pressure loss.
Upon conclusion of the investigation a summary of findings and recommendations was presented to the client encompassing as-built drawings, calculations, a summary of works and recommendations for resolution.
Rotary Breaker Facility Upgrade
The layout of the Rotary Breaker Reject Facility at Glencore's Collinsville Open Cut Coal Mine required loaders to be fully articulated to access and remove material from the reject bin. Orana Engineering provided a proposal for re-orientation of the facility 90 degrees, allowing loaders to drive directly into the bin area for removal of material.
The aim of proposed changes was a reduction in safety risks posed by awkward positioning of the facility. The design scope included modifying the existing reject chute to reduce blockages and other operational issues. The new design allowed for greater clearance of reject material and with the chute supported off the side wall of the facility to ensure structural integrity.
Orana Engineering designers prepared a 3D model considering limited vehicle interactions, optimising loading operations and minimising risks of structural damage. IFC drawings and project management were provided to complete the installation through to commissioning.
Skip Rotator
Glencore’s Ernest Henry Mine proposed to install a skip rotator to enable periodic maintenance and refurbishment of its underground ore hoist skips. The skip rotator was to consist of a removable access platform, a two-part skip cradle, plus a pneumatic drive motor and brake assembly supplied by the compressed air system. It was envisaged the rotator would enable ore skips to be rotated without the use of a 20T mobile crane and a 32T forklift which was the established method.
Orana Engineering was requested to provide mechanical and structural design and drawings of sufficient detail to allow fabrication, installation and operation of the skip rotator. In addition, Orana Engineering mechanical design personnel generated a model of the skip rotator using Autodesk Inventor which provided the client with a 3D overview of the design.
Conveyor Counterweight Design
Orana Engineering was approached by Glencore’s Oaky Creek Coal CHPP personnel to supply a cost estimate for development of modified winch systems for its CV15 and CV16 take-up towers.
The scope of work included provision of mechanical, structural and electrical engineering and design drafting for inclusion of electric take-up winches to facilitate lowering of conveyor counterweights during maintenance activities.
Structural and civil checks were conducted to account for expected force changes caused by additional sheaves and electrically driven winching effects on the structures when compared to the existing gravity take-up applications. The installation was configured and commissioned into the DCS control system by Orana Engineering's control systems engineers.
In addition to mechanical and electrical detailed design drawings, Orana Engineering provided equipment recommendations and specifications, bill of materials and a Safety In Design Report upon finalisation of the design development cost estimate.
LOM Raw Water Supply Plan
Raw water pressure problems within the longwall and development mining areas at Xstrata Coal's Oaky No.1 Underground Coal Mine had resulted in numerous production delays. At the client’s request, Orana Engineering undertook a Life of Mine (LOM) study to develop a raw water supply plan based on strategic booster pump positioning.
Hydraulic modelling was subsequently completed by Orana Engineering based on the Raw Water Supply Network LOM Study and taking into account the effects of firefighting demand pressures, flow rates and water hammer.
Results were summarised in a pump positioning flow sheet and a pump positioning plan to illustrate recommended current and future booster pump positions required to achieve minimum raw water supply pressures and flow rates.
Mine Dewatering
At the request of Carborough Downs Coal, Orana Engineering initiated an investigation into an upgrade of dewatering and sump transfer systems for multiple underground and surface mining areas at the then Vale-owned mine. Existing pumping systems were deemed not fit for purpose and the client required options for solutions capable of handling projected maximum rainfall and underground water-make intensities and preventing ingress of water to mine workings during such events.
In addition, Orana Engineering was requested to formulate a concept design for dewatering of underground workings during longwall mining operations and to offer alternatives to the existing system.
At the conclusion of investigations, the client was provided with various concept designs for both surface and underground dewatering options along with equipment recommendations and budget estimates.
CHPP Samplers
Orana Engineering provided client engineer and project management support for the design and installation of a new product coal sampler at Glencore's Collinsville Mine CHPP. The scope also included civil engineering support and design drafting for the concrete footings which were out of scope for the sampler supplier.
Orana Engineering's project manager provided onsite support as required to deliver the multidisipline design and installation taking into account the requirements of site stakeholders in the brownfield site.
Tertiary Crusher Upgrade
Orana Engineering was called upon by Glencore's Collinsville Open Cut Coal Mine to provide engineering, drafting and project management for an upgrade to its tertiary crusher and supporting structure, involving multiple site visits to assist with on-site aspects of the construction phase.
The basis of design included engineering and drafting to understand and develop the FEED and scope for the capital project, designing of the support structure to install the replacement tertiary crusher and provision of package management for the entirety of the project.
Some of the primary deliverables for the project included 36x IFA / IFC drawings for the tertiary crusher structure upgrades, a critical spares list (including liaison with vendor), fabrication scope of work for tendering, a Change Management document, and a Risk Assessment.
PPP027 Plant Feed Upgrade
Century Mining’s zinc tailings treatment operation is situated in north-west Queensland and is the largest tailings retreatment operation in Australia. Century sought the services of Orana Engineering in providing engineering support for its PPP027 Plant Feed Upgrade Project.
The project scope encompassed multidisipline engineering design for the upgraded plant feed pumping system including Weir Warman pumps. The client also requested a mechanical engineering review into combined use of poly lined, rubber lined and UHMWPE piping supported by Orana Engineering’s liaison with product vendors. Electrical design and site based support was delivered by Orana Engineering to suit the requirement of the project resources and timeline. Civil and structural engineering design was completed for the underground services and concreted area and footings.
Gravity Take-Up Access Platform Audit
Orana Engineering undertook an audit of ladders, steps and walkways associated with the Collinsville Open Cut CHPP gravity take-up (GTU) access platforms. A desktop audit was completed from photos and technical information gathered on site and with reference to AS1657 "Fixed Platforms, Walkways, Stairways & Ladders - Design, Construction & Installation" and the client's own standard for ladders, steps and elevated walkways.
At the conclusion of the audit, a letter of recommendation was provided to Collinsville Open Cut, documenting audit findings, cross referencing photos and detailing remedial action necessary for compliance. Signage requirements were also determined within the scope of the audit and included in audit recommendations.
Yard Machine Upgrades - 3D Scanning
Glencore's Collinsville Open Cut Coal Mine requested the assistance of Orana Engineering in conducting 3D laser scanning of its stockyard mobile equipment comprising raw, clean and bypass coal stackers as well as a raw coal reclaimer.
Scanning was carried out during a four day shutdown, utilising Orana Engineering's Faro 3D Laser Scanner. Upon return from site, post-processing of files was completed and scan data prepared for issue to the client.
At the conclusion of the assignment, scan data was provided in a format suitable for interrogation by others in 'issued for use' format.
APA Group Tender
APA Group released a project for tender comprising electrical and instrumentation for rectification of hazardous area compliance issues. Condamine Electric Company (CEC) tendered on the work and engaged Orana Engineering to prepare a detailed estimate of costs to complete the rectification works.
Orana Engineering undertook a detailed review of the scope and drawings in the tender package to ascertain requirements. Quotes for non-standard equipment were obtained and a detailed cost estimate was created. Additionally, from the scope review Orana Engineering identified and compiled a comprehensive list of questions which were subsequently raised by CEC during a tender site visit. Upon provision of responses, Orana Engineering delivered a complete capital estimate to CEC for tendering.
22M Flyover Conveyor
Oaky Creek Coal engaged Orana Engineering to perform electrical and control system design aspects of a 22M Flyover Conveyor to provide an interface between two existing conveyor systems.
Orana Engineering’s brownfield engineering expertise was drawn upon to resolve complexities in interfacing two different coal streams, powered from separate substations and controlled from independent process control systems. Should one system need to be shutdown it was necessary that the other system was not impacted.
The electrical engineering scope included powering the conveyor and transfer systems and providing lighting designs and power distribution. Control system engineering included selection and specification of instrumentation, specification of control system hardware and development of a functional specification.
Ball Mill No. 2 Recommissioning
Eloise Copper Mine required recommissioning of their No.2 Ball Mill. During recommissioning it was identified that a means of relocating grinding media to the feed chute needed to be designed and engineered, with RPEQ certification. Orana Engineering was contacted to assist and a monorail, complete with electric hoist and trolley, was identified as being the practical solution.
Challenges presented themselves while locating the monorail within the existing structure, however Orana Engineering was able work within the constraints of the existing structure to meet client requirements. All elements of the structural engineering review and design of the monorail to were taken into account.
RPEQ certified fabrication and installation drawings were produced, ensuring the upgraded structure was fit for purpose.
CHPP Conveyor Capacity Audit
Vale at Carborough Downs Coal Mine required quantifying of current and possible future capacities of product conveyors at their coal processing plant in Central Queensland and high level recommendations to achieve increased plant tonnages.
Orana Engineering completed an initial site visit to gather the necessary information for a review of each of the conveyors. Engineering checks were completed to identify bottle-necks in the conveyor design such as motor power, drive equipment, belt curves, GTU mass, belt speed, belt capacity, belt tensions and electrical supply.
Orana Engineering issued a detailed report at completion of the study and provided concept level equipment modification recommendations for tonnage ranges advised by Carborough Downs Coal Mine.
Crane Lifting Beam
The mother beam of the 40T ship loading crane at the Port of Townsville was nearing the end of its 30 year service life. Xstrata Copper engaged Orana Engineering to redesign the beam based on the existing beam and to incorporate changes in compliance with latest regulations.
After fully modelling the mother beam using Autodesk Inventor, RPEQ approved shop detail drawings were produced. Electrical monitoring systems were introduced to enable crane operators to confirm when the mother beam was fully engaged with various attachments, and control wiring to the beam was redesigned to include two cable drums whereas the original had three.
Mechanical redesign included a failsafe back-up locking system and design improvements highlighted by feedback from maintenance personnel.
Crusher Circuit Upgrade
Eloise Copper Mine purchased a Metso dual deck vibrating screen to replace an existing smaller screen and a second Omnicone cone crusher to provide a secondary crushing circuit for increased production and efficiency. Orana Engineering was engaged to develop a design solution and detailed drawings for the secondary crushing circuit which utilised as much existing equipment as possible.
Orana Engineering was able to provide an efficient, practical design solution while minimising the associated design costs to provide site personnel with information required to refurbish and install the conveyor equipment necessary for the crushing circuit.
Orana Engineering successfully completed the design within a tight project time frame and produced in excess of 100 detailed drawings.
Cyanide Tank Upgrade
Carpentaria Gold identified that bunding around their Ravenswood cyanide storage tank was inadequate. Sodium Cyanide, used in the gold recovery process, is potentially lethal to humans and animals and detrimental to the environment. It is necessary to ensure it can be safely contained in an emergency.
Orana Engineering provided an innovative solution comprising a smaller tank fitted inside the existing tank. The design minimised loss of storage capacity by providing a smaller tank for primary storage whilst maintaining the existing external tank to act as the bund.
Utilising the existing tank as a bund, Orana Engineering delivered a design that met the client brief while re-using the majority of major tie-in points and providing improved access for maintenance.
F100 Reagent Modifications
Orana Engineering was engaged by MMG's Century Mine to review a proposed reagent dosing system within the concentrator.
An investigation was conducted which included hydraulic modelling for various reagent dosing system philosophies. Results were presented for a range of design and operating conditions and three solutions were proposed meeting the client's requirements. Factoring in control system complexity and cost, Orana Engineering recommended a preferred option and a back-up option requiring only minor system modifications.
The engineering review was completed within a short timeframe and a detailed report provided to MMG detailing hydraulic modelling results and required operational settings for the offered options. MMG was able to use the results to make a decision on the solution ultimately implemented.
Flotation Cell Upgrade
To increase the efficiency of their concentrator, Eloise Copper Mine enlisted Orana Engineering to provide engineering and design assistance with installation of three copper concentrate scavenger cells within the existing plant.
3D models created by Orana Engineering designers were used to visually communicate solutions for new and existing equipment locations and structure arrangements. Detailing of these concept models enabled Orana Engineering to identify key tie-in locations within the plant for survey during the detailed design phase.
A multidisciplinary approach during detailed design ensured improved efficiency, with brownfield engineering challenges in relocating / connecting to existing equipment successfully achieved. Upon design completion the client was provided with an installation drawing set and scope of work.
Gold Slurry Sampler
Orana Engineering was engaged to design new sampling equipment for improved sampling effectiveness at Carpentaria Gold’s Ravenswood operations.
A site visit was undertaken by Orana Engineering design staff to accurately record critical data. This enabled designers to produce a detailed 3D model which was used extensively during interactions with the client and ensured a fluent understanding of the project scope by both parties throughout the design process.
Orana Engineering was able to integrate new sampling equipment into the existing plant whilst minimising any impact on the operation. Various challenges were overcome with the result being successful delivery of drawings for fabrication and installation of equipment, allowing improved sampling and production reconciliation whilst minimising impact to operations.
Heavy Vehicle Washdown Facility
MMG's Karumba Port Facility engaged Orana Engineering to design a heavy vehicle washdown facility to assist with management of concentrate for site vehicles and machinery. The time frame was short due to operational requirements, such that Orana Engineering worked from concept to IFC drawings in just seven days.
The design needed to accommodate a number of different vehicles from fully laden container trailers to a 30 tonne forklift, whilst also ensuring ease of facility maintenance and capture of runoff for environmental compliance.
Concept sketches were prepared, from which a detailed design was developed to meet client requirements. Through effective communication with the client Orana Engineering was able to deliver the design in a compressed timeline, to specification and budget.
Inner Bypass Valves
Orana Engineering was engaged by MMG's Century Mine to design an upgrade within the concentrator for increased flow from a flotation cell to a tailings trough.
Orana Engineering conducted a concept investigation of available options to increase the flow rate. Results were presented for a range of design and operating conditions, and a preferred option was selected for detailed design.
Orana Engineering design staff created a 3D model of the new pipeline using Autodesk Inventor. The 3D model was used to produce fabrication drawings for pipe supports, new platform and new pipe bridge. Drawings also included isometric pipe spool drawings and revised P&ID drawings.
Jaw Crusher Platform
The maintenance department of Eloise Copper Mine contacted Orana Engineering with a requirement for design of an access platform for their jaw crusher, including engineering certification and drafting. The client provided site measurements and a basic concept of the design they were looking for.
Being a brownfield engineering project, the design had to consider the surrounding area and existing structures to minimise modifications. Autodesk Inventor was used to create a basic 3D model of the area. Once the physical data was established the detailed design of the platform was able to be performed efficiently.
Orana Engineering was able to produce both detailed shop drawings for fabrication and site installation drawings, all of which were provided with structural engineering certification.
MG07 Conveyor – Chamber Design
Carborough Downs is an underground operation utilising conveyors to transport mined coal to the surface. As new longwall headings are mined, new conveyor installations are also required. Orana Engineering was engaged to complete a drive-head chamber design, ensuring adequate sizing for installation of conveyor equipment.
During initial mining of the chamber, a coal seam fault line was discovered. Carborough Downs requested that Orana Engineering develop a chamber design that maximised product mined through the fault area, while working within conveyor installation constraints. Using AutoCAD, Orana Engineering produced several design options and sketches for client approval and reference during mining processes.
Orana Engineering provided final chamber excavation drawings, which were developed into mine designs and sequence plans, by site mining engineers.
MG08 Development Conveyor
Carborough Downs Coal Mine is an underground operation utilising conveyors to transport mined coal to the surface for processing. As operations progress and new longwall headings are mined, new conveyor installations are also required.
Orana Engineering was engaged to design a new longwall drive-head chamber and conveyor installation, initially providing a drawing set detailing required drive-head chamber dimensions to suit the conveyor installation.
Using AutoCAD, a civil design and conveyor equipment arrangement was produced. The conveyor design had to consider several constraints, including available equipment, transfer tie-in to existing trunk conveyor, maintenance access, drainage, minimum clearances and belt curves.
Upon layout approval, AutoCAD drawings were produced detailing civil and mechanical design aspects, enabling site engineers to complete installation with efficiency while ensuring regulatory compliance.
MIBC & Diesel Upgrade
The purpose of the Reagent System Upgrade at Oaky Creek was installation of new reagent storage tanks, discharge / delivery pumping systems and automated flow control distribution manifolds for the delivery of each reagent to the nominated process connections.
Orana Engineering performed mechanical, electrical and control systems design, drafting and engineering for the project. The primary deliverables included scope of works, construction drawings, functional specification, BOM, spares lists and equipment / instrument data sheets.
Orana Engineering managed the onsite commissioning of the system and provided a system handover to operations for implementation. An Operation & Maintenance Manual and Hazardous Area Dossier were provided on project completion.
Mobile Plant Electrical Drawing Books
For personnel safety and compliance with Queensland’s Coal Mining Safety & Health Regulation it is a requirement for mine sites to provide electrical workers with access to up-to-date drawings for electrical equipment and electrical installations.
To improve the maintainability of plant electrical systems and personnel safety, Hail Creek Mine engaged Orana Engineering to create bound books of electrical drawings for Draglines 1 and 7 and Shovel 14. Multiple books were made for each machine in both A4 and A3 sizes and using waxed (waterproof) paper to ensure longevity.
Using vendor drawings from the client, Orana Engineering produced bound books containing all electrical power, control and termination diagrams associated with the respective mobile plant.
Reagents Lightning Protection
To ensure the CHPP reagent tank farm lighting protection systems complied with Australian Standards, Moranbah North Coal requested Orana Engineering to undertake a review and design an upgrade of the lightning protection systems for the tank farm area.
With the area encompassing fuel storage tanks, it was classified as having structures with "explosive or highly flammable contents" and was therefore required to comply with AS1768:2008 Lightning Protection. Orana Engineering’s audit of the installation and its lightning protection systems confirmed that an upgrade of the facility was needed to comply with current lightning protection standards.
Utilising its team of detailed drafters Orana Engineering created a set of drawings detailing the work required to comply with AS1768:2008 Lightning Protection.
Redraw Dragline DL007 Drawings
To improve the maintainability of plant electrical systems and personnel safety, Hail Creek Mine employed the drawing revision services of Orana Engineering to redraw electrical power, control and termination diagrams associated with its Dragline 7 into AutoCAD format.
Having electrical drawings in CAD (computer aided design) format, is one of the most efficient ways to capture site electrical modifications, installations or as-building changes for ready access by site personnel involved in maintenance and operations.
Working closely with site contacts and onsite electricians, Orana Engineering was able to accurately reproduce 247 electrical drawings into AutoCAD for Dragline 7.
Sewage Treatment Plant Refurbishment
To increase productivity and maintain compliance with legislative standards, Glencore Oaky Creek Coal employed the services of Orana Engineering to design and manage the electrical aspects of an upgrade to their existing sewage treatment plant.
The project was managed on-site by others, with Orana Engineering providing electrical engineering, design, project management and construction / commissioning assistance.
Upon completion of installation, Orana Engineering updated all drawings to reflect any changes made, thus providing Glencore Coal with as-built drawings which will make any future maintenance or fault-finding work more efficient and cost effective, as well as providing legislative compliance.
Tailings Pumping System - As-Built
At the completion of tailings pumping upgrades of the main CHPP and Module 4 CHPP at Oaky Creek Coal, Orana Engineering received as built drawings from site and was requested to make electronic revisions for upload into the client’s Drawing Management System.
Over 80 drawings had received red pen site mark-ups indicating either that the design had been constructed as per the drawings, or highlighting design changes made during the construction phase of the project. Orana Engineering reviewed these mark-ups and formally revised all drawings to as built status, incorporating the site mark-ups.
The final set of drawings was uploaded to the client’s Drawing Management System ensuring site personnel had access to the latest as built drawings.
Tank Static Line
Management at Carpentaria Gold’s Ravenswood Operation enlisted Orana Engineering to design a fall arrest system that could be easily removed and repositioned above multiple leach tanks, allowing for safe removal and servicing of tank agitators.
From a site visit, Orana Engineering identified the need for an arrangement that could be easily disassembled and relocated to each leach tank. The design was challenging due to the varying nature of access structure members above tanks.
Orana Engineering designers proposed an assembly utilising a common set of supporting columns with struts of varying lengths depending on the work location. A full set of shop fabrication and assembly drawings were issued with the final design providing safety for personnel working above open tanks.
TC04 Trunk Conveyor Extensions
Carborough Downs Coal Mine is an underground operation utilising conveyors to transport raw material to the surface for processing. As operations progress new trunk conveyor extensions are required.
Orana Engineering was engaged to assist with the process of extending an underground trunk conveyor. This involved using survey data of the conveyor heading and designing a suitable belt profile, utilising minimum conveyor curves identified in the conveyor power and tension analysis.
Orana Engineering produced a set of drawings detailing the belt profile, conveyor structures and locations for roof bolts that the structures would be suspended from. These drawings enabled site engineers to complete the conveyor structure installation and conveyor extension with minimal risk of error and conveyor tracking problems.
Tippler Refurbishment Feasibility
Glencore Port Operations in Townsville operate an export facility for minerals concentrate and refined copper within the Port of Townsville precinct. The concentrate in-loading rotaside tippler was identified as being at end of life and a feasibility study was commissioned to review a like-for-like replacement option for refurbishment of the tippler.
To facilitate feasibility-level costing, Orana Engineering was asked to provide electrical engineering and mechanical engineering assistance with provision of a concept design for the proposed refurbishment and upgrade.
By working closely with Glencore, and other consultants engaged on the project, Orana Engineering was able to contribute as part of a collective "owners engineering team" to the feasibility assessment of a significant engineering project in the Townsville Region.
TK102 Bypass Piping
When tasked with a major repair to one of their leaching tanks, personnel at Carpentaria Gold's Ravenswood Operations enlisted the assistance of Orana Engineering to develop a solution that would allow process operations to continue whilst leaching tank TK102 was out of service.
A site visit and discussions with the client suggested the installation of a bypass line around TK102. By utilising site information, Orana Engineering designerswere able to detail a new bypass line through the existing processing plant area. This involved minor modification of existing structural steel and addition of pipe supports for the new HDPE bypass pipeline.
Bypass piping was successfully installed during normal operation with only tie-ins needing to be installed during a single shut down.
Treated Water Boost Pumps
Oaky Creek Coal uses an onsite reverse osmosis plant to provide treated recycled water to various site operations. An opportunity was identified to use this recycled water for supply to critical equipment such as horizontal belt filters, thereby improving equipment water quality, reducing equipment downtime and lowering maintenance requirements.
Orana Engineering reviewed the performance of two existing boost pumps intended to provide high pressure treated water to a new horizontal belt filter. Hydraulic modelling was performed to predict future demand and thus determine the suitability of the existing pumps for use in the new application.
Orana Engineering also prepared a control philosophy for use by systems engineers to ensure safe operation of the pumps under all operating conditions.
UG Conveyor Installations – MG32 Tripper Chamber
At Glencore’s Oaky No.1 underground coal mine, transportation of vast quantities of coal over long distances requires significant power. Often drive-head power is insufficient or constrained by allowable belt tension and an additional drive or power source is required to meet operating capacity. Additional power is commonly sourced from a driven conveyor tripper installed along the conveyor with appropriate excavation for the tripper.
Using the client’s existing mine plan to position the new tripper chamber, Orana Engineering design drafting personnel worked with site engineers to assess required chamber dimensions while simultaneously minimising the excavation of material.
Orana Engineering used AutoCAD to produce a drawing set detailing the mining required, and an overlay showing future equipment installations within the new chamber.
UG Conveyor Installations – MG32 Tripper Civil Design
Engineers at Glencore’s Oaky No. 1 underground coal mine engaged Orana Engineering to determine civil work requirements to install tripper equipment on the MG32 longwall conveyor. On completion of chamber mining, finished surfaces (rib and floor) may require modification for the installation of conveyor tripper equipment. The civil design must determine concrete grades for drainage, safe access and reinforcing for conveyor equipment, while minimising trimming and concrete required.
Manipulating “as-cut” survey data using AutoCAD, Orana Engineering design staff could accurately determine where tripper equipment could be installed with minimal trimming and concreting. A drawing set was produced detailing civil aspects of the tripper design, including chamber trimming, equipment mounting locations, configuration of reinforcing and relative concrete levels for drainage.
UG Conveyor Installations – MG32 Tripper Mechanical Design
Orana Engineering was engaged by Glencore to design and install a detailed arrangement of tripper drives, brakes, pulley frame and load station for the MG32 conveyor at its Oaky No.1 underground coal mine.
Mechanical design considerations included operating capabilities, unimpeded travel road access and minimum belt curves. The design was dependent on the civil installation previously detailed by Orana Engineering. Often equipment is simply re-located from previous installations with minor modifications. Orana Engineering has developed unique methods for completing this type of design efficiently and at reduced cost to our clients.
AutoCAD was used to develop a mechanical design, from which a drawing set was produced that detailed out the mechanical aspects of the tripper installation
UG Conveyor Installations - MG Chamber Design
Mining millions of tonnes of material requires significant infrastructure and planning. Orana Engineering has been engaged on multiple occasions at Glencore’s Oaky No. 1 underground coal mine, to design new conveyor drivehead chambers to install equipment for longwall mining.
Using the client’s existing mine plan, Orana Engineering design drafting personnel worked in tandem with engineers to assess required chamber locations and dimensions, with consideration to the size and orientation of equipment to be installed and minimising the material to be excavated.
An AutoCAD drawing set was produced detailing the extent of mining required along with an overlay showing future equipment installations, enabling the client to efficiently complete chamber mining with a design suitable for future installations and minimal rework.
UG Conveyor Installations - MG Civil Installation
Engineers at Glencore’s Oaky No. 1 underground coal mine engaged Orana Engineering to determine civil work requirements to effectively utilise drive-head equipment in newly mined chambers for conveyor installations.
On completion of chamber mining, finished surfaces (rib and floor) may require modification for installation of the conveyor drive-head equipment. The civil design must determine concrete grades for drainage, safe access and reinforcing for conveyor equipment, while minimising trimming and concrete required.
Manipulating “as-cut” survey data using AutoCAD, Orana Engineering design staff could accurately determine where equipment might be installed with minimal trimming and concreting. A drawing set was produced detailing civil aspects of the conveyor design, including chamber trimming, equipment mounting locations, configuration of reinforcing and relative concrete levels.
Yokogawa DCS Upgrade
Since 2005, Orana Engineering has provided 24/7 support for Glencore's Oaky Creek Coal control systems. At the CHPP a Yokogawa DCS installed in 1998 is used as the primary control system. With existing CentumCS Unix software no longer supported by Yokogawa, it was essential to complete an upgrade to the CentumCS3000 system.
Orana Engineering developed conversion tools to allow configuration data to be extracted from the CentumCS Unix platform and imported into the CentumCS3000 environment. These tools provided efficiency and accuracy for the conversion and delivered a significant cost saving.
The quality of conversion tools and simulation programs developed by Orana Engineering resulted in highly efficient site commissioning, completed without plant downtime.